At the end of the first Iteration, the team finishes User Stories A, B, and 50% of C. The Story sizes are set at these points: Story A = 8 points Story B = 1 point Story C = 5 points Story D = 3 points What is the team's velocity?
Three members of Team C created a new workflow to speed up the testing process. They spent an entire Iteration designing the process but discovered, just before implementation, that the system could not support the workflow. The rest of the Team was excited to hear what was learned from the failed experiment. Which of the following characteristics of a high-performing Agile Team is Team C demonstrating?
During Iteration Planning, the Product Owner (PO) introduces a new story to the team. They cannot come to a consensus on the size of the new story and ask the PO for more details. After a lot of discussion, multiple dependencies with other teams emerge, so the team decides to leave the story in the Team Backlog and not commit. Is the team's response an anti-pattern?