The influence of the supply chain network can enable an organisation to benefit from increased absorptive capacity. What is meant by 'absorptive capacity'?
Raincoat Incorporated is running a project with two major activities. Activity 1 will start on the 1st January and finish on the 1st June. Activity 2 will start just before the completion of Activity 1, so approximately the 15th may (providing there is no delays) and run until 31st December. What type of sequencing is being used by Raincoat Incorporated?
Ian is a Project Manager for a large construction project involving the building of a new hospital. A complex supply network is involved which includes the use of several subcontractors. Which of the following would be the best method for dealing with subcontractors for this project?