You change an active project baselineand save it. Then, the system creates a new baseline.
What are the statuses of the previous baseline and new baseline?
An employee's time recording method is set to "POSITIVE". The employee is assigned a clock-time based
work.
schedule. The working hours are defined to be from 8:00 to 17:00.
The employee is also assigned to a working timeaccount, where planned working hours are capped.
The employee records two time entries for a particular day.
The first is from 9:00 to 15:00, and the second entry is from 17 :00 to 21 :00.
What is the posting quantity for this date in the working time account?