Special Offer! Sale of the Month | Extra 20% Off - Ends In Coupon code: DG2020

Free SAP C_BYD15_1908 Exam Questions

Absolute Free C_BYD15_1908 Exam Practice for Comprehensive Preparation 

  • SAP C_BYD15_1908 Exam Questions
  • Provided By: SAP
  • Exam: SAP Certified Application Associate - SAP Business ByDesign Implementation Consultant
  • Certification: SAP Certified Application Associate
  • Total Questions: 80
  • Updated On: Jan 26, 2025
  • Rated: 4.9 |
  • Online Users: 160
Page No. 1 of 16
Add To Cart
  • Question 1
    • What is the correct priority and sequence to determine the cost rate in case of an internal service confirmation? 

      Answer: A
  • Question 2
    • Which additional supplier roles can you assign to a supplier business partner? Note: There are 3 correct answers to this question. 

      Answer: A,C
  • Question 3
    • You change an active project baselineand save it. Then, the system creates a new baseline. What are the statuses of the previous baseline and new baseline?

      Answer: D
  • Question 4
    • An employee's time recording method is set to "POSITIVE". The employee is assigned a clock-time based work. schedule. The working hours are defined to be from 8:00 to 17:00. The employee is also assigned to a working timeaccount, where planned working hours are capped. The employee records two time entries for a particular day. The first is from 9:00 to 15:00, and the second entry is from 17 :00 to 21 :00.
      What is the posting quantity for this date in the working time account? 

      Answer: A
  • Question 5
    • Which of the following entities are supported by projects in SAP Business ByDesign? Note: There are 3 correct answers to this question

      Answer: A,B,D