  • Question 1
    • Topic 4, Defect Management

      Defect Management
      Consider a defect report and assume that a part of its lifecycle includes the following
      states:
      New: Is the initial state
      Working: Means that the developers are addressing the defect in order to produce a fix for
      the defect
      Clarification: Means that the developers need more information from the tester to address
      the defect and produce a fix for the defect and the tester is working to provide this
      information to the developers
      Verification: Means that a fix for the defect has been produced and the tester is running the
      adequate tests to verify whether the fix solves the defect
      Closed: is the final state
      Which of the following answers represents an invalid sequence of states that can’t lead the
      bug report to the “Closed” state?
      Number of correct responses: 1
      K2 1 credit
       

      Answer: C
  • Question 2
    • Topic 2, Test Management

      Test Management
      Which of the following statements about management of product quality risks in mature
      organizations with respect to the lifecycle, is true?
      Number of correct responses: 1
      K2 1 credit 

      Answer: B
  • Question 3
    • Test Tools and Automation
      In your organization the following tools of the same vendor are currently in use: a
      requirements management tool, a test management tool and a bug tracking tool.
      You are the Test Manager.
      You are currently evaluating a test automation tool of the same vendor (to complete the
      vendor's tool suite) against an interesting open-source test automation tool under the GNU
      GPL (General Public License).
      There are no initial costs associated to that open-source tool.
      Which of the following statements associated to the selection of the open-source tool is
      correct in this scenario?
      Number of correct responses: 1
      K2 1 credit


      Answer: B
  • Question 4
    • Test Management
      You are managing the system testing for a SOA based system. The integrated system
      consists of several subsystems:
      - a SOA middleware
      - a CRM (Customer Relationship Management) system
      - a BRM (Billing and Revenue Management) system
      - a SMS (Subscriber Management System) system
      and you performed a risk analysis based on these subsystems.
      At the end of the scheduled period for test execution you produce a first classical report
      based on the traditional metrics of testing. Test pass/fail status and bug status
      (open/resolved) That table provides you a distorted picture of the quality risk, because
      there is no indication of the risk level of the failed tests, the tests not run, or the open bugs.
      Thus, you produce the following table to solve this distortion issue:

      CTAL-TM-Syll2012-page54-image29

      In the table above, where you have introduced the concept of risk weighting, the highest
      risk test or bug report has a score of 1, while the lowest risk test or bug report has a score
      of 0.04.
      Which of the following subsystems, based on the risk scores of the table, is most risky?
      Number of correct responses: 1
      K4 3 credits 

      Answer: B
  • Question 5
    • Test Management
      You are the Test Manager of a new project aimed at developing a software system that
      must be certified at level B of the DO-178B standard. The project will follow a V-Model
      software development life cycle and it will have four formal levels of testing: component,
      integration, system and acceptance testing.
      You must produce the test plan documentation for this project by providing an adequate
      coordination across the four levels of testing in order to assure auditability.
      Which of the following answers would you expect to best describe how to organize the test
      plan?
      Number of correct responses: 1
      K3 2 credits

      Answer: C